business

Ajumako 24-hour economy market 9% complete; traders raise concerns over project location

Ajumako 24-hour economy market 9% complete; traders raise concerns over project location

The construction of a 24-hour economy market in the Ajumako-Enyan-Essiam District in the Central Region, which commenced in April this year, is progressing steadily, with nine per cent of the work completed. A Ghana News Agency (GNA) visit to the project site at Enyan Abowinum, about five kilometres from Ajumako, the district capital, on Wednesday showed workers on site, with some foundation work underway.

The construction of a 24-hour economy market in the Ajumako-Enyan-Essiam District in the Central Region, which commenced in April this year, is progressing steadily, with nine per cent of the work completed.

The multi-facility project, scheduled for completion in 24 months, will include commercial buildings housing banks and other businesses, lockable shops, market sheds, an abattoir, food courts, and a fire station, among other facilities.

A Ghana News Agency (GNA) visit to the project site at Enyan Abowinum, about five kilometres from Ajumako, the district capital, on Wednesday showed workers on site, with some foundation work underway.

Workers cleared part of the four-acre land earmarked for the project to make way for the initial works, while a significant portion, which appeared to be farmland, remained unclear.

The GNA also saw granite chippings, an excavator, a concrete mixer, and iron rods at the site. They also drilled a borehole, and a workers’ accommodation facility was under construction.

Mr Francis Atinyo, the Project Engineer, told the GNA that construction was currently focused on the lockable shops, which were 12 per cent complete.

He noted that excavation was complete; reinforcement mats and column works had been undertaken, with concrete casting scheduled to begin soon, followed by substructure blockwork.

He explained that construction of all facilities was expected to run concurrently, but discrepancies in the architectural design had delayed work on most of them.

He said the original building designs were larger than the available site, requiring the consultant to revise the plans and adjust the positioning of the structures.

He expressed hope that the revised designs would be ready before the end of the week, allowing work to proceed in earnest.

That notwithstanding, the engineer maintained that the project remained on schedule, assuring that it would be completed within the stipulated 24 months, provided the government fulfilled its financial obligations.

“So far, we are receiving funding regularly, and there is nothing that has hindered that because the certificates that have been raised have been honoured by the clients,” he said.

Unlike the Big Push Road projects in the district, Mr Atinyo said the rainy season had not affected their work, and they had not encountered any disputes with landowners.

He noted that the project was creating employment and business opportunities for residents, as most labourers came from local communities, with some workers from Accra.

Additionally, they sourced some construction materials, including wood, locally.

“By December, we should be done with the foundation work for all the buildings so that from January, we will start with the superstructure. By July, at least, some of the commercial buildings should be ready,” the project engineer assured.

Meanwhile, some traders in the area have expressed concern about the market's location and the lack of alternative trading spaces for those being displaced by ongoing road construction.

They said Abowinum was relatively far from the district capital, Ajumako, and other communities, making it difficult for traders and customers to access the market.

Uncle Fii, a shoe and bag seller, lauding the initiative, said the market would have served traders better if it had been located in the centre of Ajumako, where it would be more accessible to residents of surrounding communities.

“It will be difficult for people from Ajumako, Ochiso, Hasowodze and other communities to travel to Abowinum to buy goods. The market should have been located in the centre of town, and so honestly, I do not think the location is suitable,” he said.

Uncle further said traders were worried about where they would operate until the new market was completed, as they were being evacuated without compensation to make way for the Big Push project.

“Where are we expected to go? Are we supposed to stay at home and watch our families go hungry? We pay three different forms of revenue to the Assembly, so the authorities should treat us fairly.

“Officials from the Assembly, together with the road engineer, were here and promised to find us an alternative place to trade. But we still do not know where they are taking us to,” he complained.

Nana Afua Abasowah, Adontenhenmaa of Ajumako Abrofoa, also disagreed with the market's location, describing it as “inconvenient” and appealing for a possible relocation.

She said business was already slow, with traders making most of their sales only on Mondays, the main market day.

She said the area became heavily congested on market days, with traders displaying goods along the roadside, creating safety risks for both traders and road users.

Affected by the Big Push, Nana Abasowah welcomed the road construction but appealed to the authorities to provide alternative trading spaces before evicting traders from their current locations.

Another trader, Comfort Baidoo, reiterated that the frequent movement of heavy-duty trucks on the road during construction increased the risk of accidents, particularly when the market became overcrowded.

She appealed to the authorities to provide a temporary trading area until the 24-hour economy market was completed.

Other traders also called for the speedy completion of the project, saying the lack of permanent trading spaces and slow sales were affecting their livelihoods.

Ms Phoebe Akyerefi, a tomato seller from Breman Essiam, urged the Assembly to complete the construction of some stalls at the existing market, which she said had stalled, before embarking on a new one.

“As for the 24-hour economy market, the authorities should expedite work to ensure its completion because we are suffering. Our goods are often left to rot because business is slow, and sales are poor,” she said.

Madam Esi Attah, a gari and maize seller, also appealed to the government to fulfil its promise to establish a bank for women, saying traders continued to depend on loans with high interest rates to sustain their businesses.

Some traders called for improved sanitation in the market and the surrounding towns.

  • project
  • market
  • ajumako
  • work
  • location
  • construction
  • trader
  • hour

Summaries and tags are generated automatically. Stay informed with VidiaNews.

Related news

Economy Palava: Traders decry rising waybill ‘store keep’ charges
business

Economy Palava: Traders decry rising waybill ‘store keep’ charges

Individuals are not left out of this ordeal Mrs. Chidinma Okafor, a tailor, recounted her ordeal saying: “My sister sent me a small carton of clothes from Lagos and paid N4,000 at the park. Ibrahim Jato, a baker, said: “I ordered baking ingredients from Onitsha for a weekend wedding cake, and the supplier already cleared the transport fare.”

Read →
Keumbu traders count losses after fire razes their businesses
business

Keumbu traders count losses after fire razes their businesses

Traders at Keumbu Market in Kisii are counting huge losses after a fire razed several businesses and buildings overnight. Keumbu Market Chairman Samwel Ombui Ongaki said they suspect the fire started in one of the stalls being used as a hotel before spreading rapidly to neighbouring businesses.

Read →
Daffiama-Bussie-Issa set for major STEM school as Jakpa, DCE inspect project
education

Daffiama-Bussie-Issa set for major STEM school as Jakpa, DCE inspect project

Director of Operations at the National Security Secretariat, Richard Jakpa, together with the District Chief Executive (DCE) for Daffiama-Bussie-Issa, James Wor, has inspected construction works on a major STEM school project in the district. Funded by the Ghana Education Trust Fund (GETFund), the project was lobbied for the district by Mr Jakpa.

Read →
Stock market rebounds as investors reap N2.2trn amid decline in oil price
business

Stock market rebounds as investors reap N2.2trn amid decline in oil price

By Peter Egwuatu The Nigerian stock market rebounded last week after weeks of sustained pressure from profit taking led to decline in stock value. Equity investors on the Nigerian Exchange Limited, NGX, last week, reaped over N2.2 trillion in capital gains leading the NGX market capitalisation, to close last week at N163.795 trillion, up from N161.593 trillion the previous week.

Read →
IC Insights expects more market-determined forex market; predicts GH¢11.6 –11.8 to one dollar in interbank market by December 31
business

IC Insights expects more market-determined forex market; predicts GH¢11.6 –11.8 to one dollar in interbank market by December 31

The International Monetary Fund (IMF), in its first review of Ghana’s Policy Coordination Instrument (PCI), emphasised that vulnerabilities persist in the foreign exchange market, particularly from the external sector, citing reserve declines that required corrective actions, which include the already transferred forex intermediation from the Bank of Ghana to the GoldBod and raising gold sale requirements for large-scale miners. In August 2026, the Ghanaian authorities and large-scale miners signed a memorandum of understanding under the GANRAP, which requires large-scale miners to sell 30.0%…

Read →