PPA CEO reviews Polavaram works, asks officials to guard against cyclone

Sanjeev Vohra calls for achieving the daily construction targets without compromising the quality of works
A view of the Polavaram project under construction across the Godavari. Polavaram Project Authority CEO Sanjeev Vohra has asked officials to protect the works from the cyclone. File
Polavaram Project Authority (PPA) Chief Executive Officer Sanjeev Vohra on Tuesday (November 17, 2026) reviewed the progress of construction works at the irrigation project site and expressed satisfaction with the pace and quality.
He called for achieving the prescribed daily construction targets without compromising quality.
During a day-long visit, Mr. Vohra, PPA Member-Secretary M. Raghuram and Chief Engineer M. Ramesh Kumar held a review meeting with officials of the Water Resources Department and representatives of Megha Engineering and Infrastructures Limited (MEIL).
The officials and MEIL representatives explained the progress of various project components. Mr. Vohra reviewed the implementation of recommendations made during his previous visits and the recent inspection by an international experts’ team.
In view of the cyclonic activity last month and fresh weather warnings, he directed officials to take precautionary measures against a possible rise in water levels and protect ongoing works from adverse weather. He sought details of the workforce and machinery deployed to accelerate construction.
Mr. Vohra inspected the earth-cum-rock-fill (ECRF) dam construction area, G Hill and G Dash Hill, among other locations. He examined the quality of soil, sand, stone, aggregates and concrete, and witnessed on-site quality tests.
He directed the project authorities and the executing agency to conduct regular quality tests and maintain proper records. He stressed the need to protect completed and ongoing works during cyclonic conditions.