Six Accra flood-control projects await Finance Ministry approval – Works Minister

Six planned interventions to tackle flooding in parts of Accra are yet to move into the construction phase as the Ministry of Works, Housing and Water Resources awaits financial authorisation from the Ministry of Finance. Dredge Masters engaged to clear Nima-Paloma drain While arrangements are being made for the main project to resume, the Ministry has turned to interim measures to improve drainage conditions in the affected area.
Six planned interventions to tackle flooding in parts of Accra are yet to move into the construction phase as the Ministry of Works, Housing and Water Resources awaits financial authorisation from the Ministry of Finance. The projects fall under the Greater Accra Resilient and Integrated Development (GARID) Project, a government initiative designed to improve drainage systems and reduce the impact of flooding on vulnerable communities in the capital.
Works, Housing and Water Resources Minister Ahmed Ibrahim says the proposed interventions have progressed to the tendering and contract award stages, but contractors cannot be given the green light to begin work until the necessary financial commitments are approved. He disclosed this in Parliament on Wednesday, November 18, 2026, in response to questions about measures being taken to address the persistent flooding that affects communities across Accra.
Among the outstanding works are the reconstruction of the Abbosey Okai Bridge, the construction of detention ponds at Atomic East and West, and improvements to the Alajo drain. The package also includes the repackaging of the Nima-Paloma drainage project and the installation of an Accra Flood Early Warning System. Mr Ibrahim explained that securing financial authorisation was necessary to complete the procurement arrangements, award the contracts and enable construction to begin.
Previous Nima-Paloma contract terminated The Minister also provided an update on the Nima-Paloma drainage project, revealing that the government had brought the previous contract to an end and was preparing to engage a new contractor. He said the project would be repackaged and re-awarded once the necessary financial commitment had been secured. Available progress figures at the time of the contract termination showed that evacuation of works had reached 13 per cent, while demolition of the existing drain stood at 25 per cent.
The casting of the concrete base had recorded 9.7 per cent progress, with the construction of concrete walls at 9.5 per cent. The figures reflect the extent of work completed before the previous contractor’s engagement was discontinued, leaving significant portions of the drainage project unfinished. Mr Ibrahim said the Ministry was working to resolve the outstanding financial and procurement issues to allow the project to continue under a new contractor.
He added that discussions were also taking place with relevant stakeholders, including the World Bank, to agree on the most appropriate procurement process for selecting a replacement contractor. Dredge Masters engaged to clear Nima-Paloma drain While arrangements are being made for the main project to resume, the Ministry has turned to interim measures to improve drainage conditions in the affected area.
Mr Ibrahim disclosed that Dredge Masters had been engaged to desilt the Nima-Paloma drain to remove accumulated materials and improve the passage of stormwater. The exercise is intended to reduce obstructions within the drainage channel and improve its capacity to carry rainwater, particularly during heavy downpours. He further indicated that additional local interventions had been introduced to protect communities along both the upstream and downstream sections of the Nima drain from the effects of flooding.
The measures are expected to help manage the immediate risks while the Ministry works towards securing the resources and approvals required to complete the larger drainage works. GARID interventions target flood-prone communities The planned projects form part of the broader GARID programme, which seeks to address some of the infrastructure and environmental challenges contributing to flooding in Greater Accra.
Through drainage improvements, detention facilities and early warning systems, the initiative is intended to strengthen the city’s ability to manage excessive rainfall and reduce the exposure of vulnerable communities to flood-related disasters. The latest disclosure by the Minister places the focus on the financial approvals and procurement processes that must be completed before the six interventions can move into construction.
- accra
- ministry
- project
- drainage
- minister
- nima
- flooding
- work





