Australia's largest proposed vegetation-fuelled power plant rejected again
A court has dismissed an appeal brought by the company behind what would have been Australia's largest modern biomass generator, in the NSW Hunter Valley.
A court has upheld the ruling to refuse a biomass power generator near Singleton, NSW.
Environmentalists say it's a huge win, but the company behind it isn't backing down.
A partnership with a data centre proposed for adjoining land is now in doubt
A court has knocked back an appeal brought by the company planning to build Australia's largest modern biomass generator in the NSW Hunter Valley.
Verdant Earth Technologies has been working to transform the former coal-fired Redbank Power Station near Singleton into a bioenergy hub since it took over the site in 2018.
The plan, initially put to the NSW Independent Planning Commission (IPC), was for it to be fuelled by invasive native species (INS) plaguing farmers in western NSW, as well as purpose-grown plants.
The proposal was for 700,000 tonnes of dry material to be burned each year to fuel the 151-megawatt proposal, which the company said could power approximately 200,000 homes.
The NSW Planning Department was told the capital investment would surpass $70 million, with the project creating 330 jobs during construction and 60 operational positions.
But the IPC last year rejected the proposal, noting the "potential benefits" for energy security and reliability, as well as employment opportunities, but ultimately ruling that the environmental impact was too great.
The NSW Land and Environment Court today dismissed Verdant Earth's appeal, upholding the IPC's refusal.
Environmentalists called the decision a victory for nature and wildlife but said state government policy needs to change to close the biomass loophole.
CEO of the Nature Conservation Council of NSW (NCC) Jacqui Mumford said she hopes the ruling marks the end of the Redbank restart.
"It was a bad project from the start," she said.
"Burning native vegetation for energy is not something that we need; there's nothing renewable or sustainable about permanently clearing wildlife, so I really hope this is the end.
Verdant Earth CEO Richard Poole told the ABC he was "totally surprised" by the dismissal.
"I'm a full believer in biomass as an absolute solution for Australia's energy problems," he said.
"I haven't seen the full judgment, but not the result we were hoping for."
Mr Poole said agreements had been made over the past 12 months to scale back the use of the invasive native species and fast-track the project's emissions reductions.
"Don't forget this waste that is in dispute is waste from INS clearing, which is a government-approved program."
Ms Mumford said the NCC would be campaigning to see the INS legislation changed, in the lead-up to the March state election.
Verdant Earth had recently entered talks with Voltic DC, managed by APDC, exploring a data centre to be built on adjoining land.
Voltic DC's website states the deal would provide "access to shared infrastructure and land to maximise data centre capacity".
"Following any restart [of Redbank Power Station], Voltic and Verdant will assess commercial co-benefits including potential power supply arrangements and shared site infrastructure."
Mr Poole said that arrangement was now in doubt.
"Obviously the hope was to solve the government's issue around renewable energy by being able to get Redbank up and provide some power to that data centre," he said.
"That's obviously not the case at this time."
Mr Poole said he would be meeting with his legal team to look at the next steps.
"We need to regroup and have a look at it. Maybe it's a data centre, maybe it's a battery site," he said.